ROAD WORKS | MID-WESTERN HIGHWAY

Published on 27 February 2025

Roads-Notice.png

 

ROAD WORKS | MID-WESTERN HIGHWAY

 

Weddin Shire Council wishes to advise that Stage 1 road works on Mid-Western Highway, approximately 35 kms East of Grenfell NSW and progressively working back to Grenfell will commence on Monday 3 March 2025.  The planned works will be carried out in 3 stages:

  STAGE         PROPOSED COMMENCEMENT DATE                                   PROPOSED CONCLUSION DATE                               
 1     MONDAY 3 MARCH 2025    FRIDAY 28 MARCH 2025
 2     MONDAY 28 APRIL 2025     MONDAY 5 MAY 2025
 3     MONDAY 31 MARCH 2025    FRIDAY 18 APRIL 2025

Note:  Work is subject to satisfactory weather conditions.

Working hours will be between 7:00am to 6:00pm from Monday to Friday, and from 8:00am - 1:00pm on Saturday's with daytime speed reductions in place during these periods.  After hours signage will be in place depending on the condition of the road however all efforts will be made to eliminate the need for after-hours speed reductions.

Possible short delays may be experienced during the road works.  Council apologises for any inconvenience, and will endeavour to act as promptly as possible.  Should you require access to property gates throughout the worksite, traffic control will assist you in a timely manner.  Essential services such as school bus runs and emergency service vehicles will be given priority during the road works.

Should you require further information, please contact Infrastructure Services Department on 02 6343 1212 during normal business hours or via email to mail@weddin.nsw.gov.au 

 

 